Asprokremmos Dam

  • Location: Paphos
  • Designer: Water Development Dept.
    • Supervisor: Water Development Dept.
    • Contract Value: €18,794,616
    • Commencement: 1978
    • Completion: 1982
    • J.V. Composition: Medcon 34% - J&P 66%

Brief Project Description:

Earthfill dam, 55m high, consisting of the main embankment, spillway, tunnels and galleries, geotechnical works and power stations. The useful capacity is 53 million cubic meters of water of surface area 2.1sq.km.