Ayia Napa – Paralimni Roundabouts
October 29, 2020

Ayia Napa – Paralimni Roads 3B and 4

  • Location: Ayia Napa, Cyprus
  • Designer: Public Works Dept.
    • Supervisor: Public Works Dept.
    • Contract Value: €10,732,423
    • Final Value: €11,913,351
    • Contract Duration: 21 Months
    • Commencement: 30/08/1999
    • Completion: 15/05/2001
    • Actual Duration: 21 Months

Brief Project Description:

Construction of 9.2 Km of new 4-lanes highway. The two directions were separated by a central lane with protective metal guardrails. A cycleway was constructed on one side and a sidewalk on the other side of the whole length of the highway. The project included secondary roads, returning points, roundabouts, traffic lights, pedestrian underpasses, storm drainage works, sewerage, and services network.