Meneou – Pervolia – Kiti – Mazotos Road
November 13, 2020Limassol General Hospital
November 13, 2020
- Location: Limassol, Cyprus
- Designer: Public Works Department
- Supervisor: Public Works Department
- Contract Value: €23,880,000
- Final Value: €22,673,417
- Contract Duration: 30 Months
- Commencement: 11/01/2010
- Completion: 31/03/2012
- Actual Duration: 27 Months
Brief Project Description:
Construction of a 4-lanes new road 2618 m long. A pressure box culvert under sea level - requiring sheet piling and dewatering - was constructed under the whole length of the road long. Works also included the laying of 2670 m of 700 mm diameter Ductile Iron sewerage pressure line and fittings, asphalt works including red asphalt at cycle ways, storm drainage works, utilities services works, walkways, retaining walls, fencing etc.