  • Location: Limassol, Cyprus
  • Designer: Public Works Dept.
  • Supervisor: Public Works Dept.
  • Contract Value: €439,111
  • Final Value: €387,666
  • Contract Duration: 5 Months
  • Commencement: 21/08/2006
  • Completion: 05/02/2007
  • Actual Duration: 6 Months

Brief Project Description

Strengthening of existing bridge using steel sections.