- Location: Larnaca, Cyprus
- Designer: Public Works Dept.
- Supervisor: Public Works Dept.
- Contract Value: €6,908,022
- Final Value: €5,821,340
- Commencement: 08/07/1998
- Completion: 13/11/1999
- Actual Duration: 16
Brief Project Description:
Runway extension and additional taxiways:Earthworks, drainage system. electrical network, asphalt laying (80,000 tons) Aprons with Pavement Quality Concrete
Works were carried out during runway closures in early morning time (01 00hrs to 08 00hrs).